Faulkners Surveyors As certified and experienced Party Wall Surveyors we specialise in all Party Wall matters.
We cover every element essential to advise upon and solve Party Wall concerns, such as:

  • Preparing and serving legitimate Party Wall Notices
  • Acting as the Structure Owners Party Wall Property Surveyor
  • Acting as the Adjoining Owners Party Wall Surveyor
  • Acting as the Agreed Party Wall Property Surveyor
  • Carrying out and preparing Schedules of Condition
  • Preparation and negotiation of Party Wall Awards

All our Party Wall Surveyors are specialists and work in accordance with the regulations set down by the Professors of Party Wall Surveyors.

The Party Wall Act etc. 1996 is law, failure to adhere to this legislation may lead to works being unlawful.

Party Wall (WikiPedia)

Normally, the contractor lays the wall surface along a building line separating 2 terraced houses, so that one fifty percent of the wall’s thickness lies on each side. This kind of wall is generally architectural. Event wall surfaces can likewise be formed by two abutting wall surfaces constructed at different times.

wall party

Party Wall Act

The Party Wall etc. Act 1996 is an allowing Act, insofar as it gives the owner of a home the legal right to carry out certain works that might otherwise make up trespass or nuisance.

It likewise looks for to protect the interests of adjacent owners from any potentially negative impacts that such works may have by imposing a requirement that all adjacent owners be offered prior notification of them.

In addition, the Act offers an obligatory dispute resolution procedure moderated by a statutorily selected property surveyor or surveyors if neighbouring owners have concerns about the execution of any proposal so alerted.

Particularly, such notification should be served where the owner of a home (known as ‘the building owner’) plans to carry out any construction work explained in Sections 1, 2 and 6 of the Act. Keep in mind that it is only those works that are covered by the Act and the scope is restricted to the following:

The information that Discovers must offer in respect of works covered the above areas is various in each case. The requirements of Area 1 and Area 6 Notices are set out in those sections but the requirements of a Notification associating with Section 2 works is set out in Section 3 of the Act. It is essential to note that the validity of any notice not supplying all the pertinent details or served in the incorrect way, could be open up to challenge in Court.

There is no basic type of Notification although many individuals use those published by the RICS or variations added to the explanatory brochure issued by the Department for Communities and Local Government. Provided all the information needed by the appropriate section of the Act is present, a simple letter would be similarly valid.

Depending upon the scenarios of any provided task there might be more than one adjacent owner on whom discover needs to be served in regard of the same work and, in the case of deep excavations, an Adjoining Owner might be aside from an immediate neighbour. It is always preferable to talk about the designated deal with adjoining owners before serving them with formal written notification – a proposal well described might reduce concerns enough to prevent a conflict developing and avoid the requirement to appoint surveyors.

There are two exceptions where the requirement to serve notice might be prevented:

  1. De minimis works: The government’s explanatory pamphlet says that some deal with a party wall might be so minor that service of notification under the Act would be generally considered as not necessary and give as examples works unlikely to impact the structural strength or support functions of a party structure or trigger damage to the neighbours side of it, such as re-plastering, shallow chasing for electrical wiring or placing power sockets, and screws to support racks, kitchen area cabinets, and so forth.
  2. Functions under Section 2 of the Act provided that composed permission is acquired from all Adjacent Owners and Occupiers before work commences.

The three types of Notice are understood, respectively as:

A party structure notification should be served a minimum of 2 months prior to the date on which it is proposed to start that work. The other two notices need to be served at least one month prior to work beginning.

The mandatory details which Sees need to include are as follows:

The majority of the pro-forma notices in use include the following info as a matter of course regardless of the type of notice:

Section 10 of the Act stipulates that where an adjoining owner does not permission in writing to works notified by the structure owner under Sections 3 and 6, both celebrations should either settle on the consultation of a single surveyor to act for both of them (referred to as the Agreed Surveyor), or each designate their own property surveyor, to identify by award matters in dispute in between the celebrations.

Where a project is straightforward, this might only include factor to consider of the time and way in which those works are to be performed. In more complex plans, believed will need to be offered to a commensurately greater number of factors and certainly designated property surveyors have the statutory jurisdiction to make an award in regard of any matter gotten in touch with any work to which the act relates.

The very same treatment is used to fix any subsequent disputes in between neighbouring owners that may develop in relation to the alerted works, consisting of any loss or damage suffered by an adjacent owner as a result of their execution.

Inactiveness on the part of the adjacent owner does not halt the statutory process. A disagreement can occur by an adjacent owner actively dissenting, that is, communicating to the structure owner an objection in respect of some matter arising out of or incidental to the works – the methods of making that objection are not important, but if he stays quiet, neither consenting nor dissenting for a period of 2 week after having been served with a Notice under either Area 3 or Section 6, the Act considers a dissent to have developed in any event.

There is no deemed dissent arrangement in Area 1 of the Act. A legitimate disagreement can still occur, and surveyors be appointed in accordance with Section 10, in respect of works alerted under that section however just as concerns actual dissent on specific grounds. An adjoining owner’s factors for challenging Section 2 and Area 6 works are rarely defined prior to the appointment of property surveyors and in most cases not even then.

Where dissent has actually emerged, whether real or considered, both owners are lawfully required to select an agreed property surveyor or, if they can not jointly settle on a single person, a surveyor each and if asked for to make such a visit by the other party, must do so within 10 days of the demand being served. Failure to comply, immediately offers the owner making the demand the statutory authority to appoint a surveyor on behalf of the recalcitrant party. This treatment is set out in section 10( 4) of the Act.

Where two surveyors are selected, they are obliged to agree upon the choice, in writing, of a 3rd property surveyor who may be called upon by either of the surveyors or either of the celebrations to figure out the challenged matters and make the essential award. The third surveyor is never appointed by anyone but the Act provides the person so selected the same statutory powers as the two property surveyors.

3rd property surveyors are most typically hired where the two surveyors have actually reached a deadlock in their deliberations over some specific point and frequently this can be in regard on the reasonableness of the costs of the property surveyor selected by the adjacent owner. Seldom will a 3rd property surveyor be asked to prepare an award in respect of the whole works but might join with one or other of the two surveyors to do so if the requirement occurs.

There is no definition of who can be a property surveyor, however it ought to not be the same individual that will supervise the works.

The award will set out the works that can be carried out, who will pay the costs for the preparation of the award and examination of the works to guarantee that they abide by the works, and who will spend for the works. If the work is exclusively for the benefit of the building owner, then they will generally be needed to pay the fees and the expense of the works.

If they disagree with the award, parties have 14 days to appeal to the county court.

The Act permits access to the adjoining residential or commercial property for the purposes of performing the works whether the adjacent owner gives permission or not, however they should be given 14 days notification.

NB: The introduction of The Party Wall etc. Act 1996 (Electronic Communications) Order 2016 implies that from 6 April 2016, notifications and other files can be served by electronic interactions.

The information that Sees need to offer in respect of works covered the above sections is various in each case. The requirements of Area 1 and Area 6 Notifications are set out in those areas but the requirements of a Notification relating to Section 2 works is set out in Section 3 of the Act. A valid dispute can still occur, and property surveyors be designated in accordance with Section 10, in respect of works informed under that area but just as concerns real dissent on specific premises. An adjacent owner’s factors for challenging Section 2 and Section 6 works are rarely specified prior to the consultation of surveyors and in many cases not even then.

Where dissent has actually emerged, whether actual or deemed, both owners are lawfully obliged to appoint an agreed property surveyor or, if they can not jointly concur on a single person, a property surveyor each and if asked for to make such an appointment by the other party, should do so within 10 days of the demand being served.

Related Articles

Around the Web