At Faulkners Surveyors we conduct Party Wall Surveys by professional and experienced Party Wall Surveyors throughout the UK.

What is a Party Wall Award?

A Party Wall Award is a contract made in between at least 2 neighbouring occupiers prior to the commencement of construction/building work which is to be carried out to a party border or structure, or where works are being carried out in close proximity to a party boundary or structure. There are 3 main types of work which need a Party Wall Property surveyor to conduct a Party Wall Award and these are:

  • Line of junction (building a brand-new wall on or alongside a limit).
  • Party Structure Functions (works to an existing party wall such as cutting into, rebuilding, thickening and so on).
  • Adjacent Excavation (excavations to a lower level within either 3m or 6m of an existing building).

In London and across the UK, our experienced business building property surveyors carry out a variety of professional surveying services consisting of Party Wall Studies (Party Wall Awards). At Commercial Building Surveyors we conduct Party Wall Studies by skilled and expert Party Wall Surveyors throughout the UK.

Party Wall (WikiPedia)

Generally, the building contractor lays the wall surface along a home line splitting 2 terraced homes, so that one half of the wall surface’s thickness exists on each side. This kind of wall is usually architectural. Event walls can also be developed by 2 abutting wall surfaces developed at various times.

wall party

Party Wall Act

The Party Wall etc. Act 1996 is a making it possible for Act, insofar as it grants the owner of a home the legal right to undertake particular works that might otherwise make up trespass or nuisance.

Nevertheless, it likewise looks for to safeguard the interests of adjacent owners from any possibly unfavorable effects that such works might have by imposing a requirement that all adjacent owners be given prior notification of them.

In addition, the Act offers a mandatory conflict resolution procedure mediated by a statutorily appointed property surveyor or property surveyors if neighbouring owners have concerns about the application of any proposal so alerted.

Particularly, such notification should be served where the owner of a property (referred to as ‘the structure owner’) intends to carry out any building work explained in Areas 1, 2 and 6 of the Act. Keep in mind that it is just those works that are covered by the Act and the scope is restricted to the following:

The details that Observes should offer in respect of works covered the above sections is different in each case. The requirements of Section 1 and Section 6 Notifications are set out in those areas however the requirements of a Notice relating to Area 2 works is set out in Area 3 of the Act. It is essential to note that the credibility of any notice not supplying all the appropriate information or served in the incorrect manner, could be available to challenge in Court.

There is no basic form of Notification although many people use those released by the RICS or versions appended to the explanatory booklet provided by the Department for Communities and City Government. Provided all the info required by the appropriate section of the Act is present, an easy letter would be equally valid.

Depending on the situations of any offered project there might be more than one adjacent owner on whom observe needs to be served in regard of the exact same work and, when it comes to deep excavations, an Adjoining Owner might be aside from an immediate neighbour. It is constantly preferable to talk about the designated deal with adjacent owners before serving them with official composed notification – a proposal well described may alleviate issues sufficient to prevent a conflict occurring and avoid the requirement to designate surveyors.

There are two exceptions where the requirement to serve notice may be prevented:

  1. De minimis works: The government’s explanatory pamphlet states that some works on a party wall may be so small that service of notice under the Act would be normally considered not essential and give as examples works unlikely to impact the structural strength or assistance functions of a party structure or trigger damage to the neighbours side of it, such as re-plastering, shallow chasing for electrical wiring or inserting power sockets, and screws to support racks, kitchen area cabinets, and so forth.
  2. Works under Area 2 of the Act offered that written permission is gotten from all Adjoining Owners and Occupiers before work commences.

The three types of Notification are known, respectively as:

A party structure notice need to be served at least 2 months before the date on which it is proposed to start that work. The other two notifications must be served at least one month prior to work beginning.

The obligatory information which Notices need to consist of are as follows:

Most of the pro-forma notices in use include the following details as a matter of course despite the type of notice:

Area 10 of the Act specifies that where an adjoining owner does not approval in writing to works informed by the structure owner under Areas 3 and 6, both parties must either settle on the visit of a single property surveyor to act for both of them (called the Agreed Property Surveyor), or each designate their own property surveyor, to determine by award matters in dispute between the celebrations.

Where a project is straightforward, this might only involve factor to consider of the time and way in which those works are to be performed. In more complex plans, believed will have to be offered to a commensurately greater number of aspects and indeed appointed property surveyors have the statutory jurisdiction to make an award in respect of any matter connected with any work to which the act relates.

The same treatment is used to deal with any subsequent disagreements between neighbouring owners that might occur in relation to the notified works, consisting of any loss or damage suffered by an adjacent owner as a result of their execution.

Inaction on the part of the adjoining owner does not halt the statutory procedure. A dispute can emerge by an adjoining owner actively dissenting, that is, communicating to the structure owner an objection in respect of some matter emerging out of or incidental to the works – the means of making that objection are trivial, however if he remains silent, neither dissenting nor consenting for a period of 14 days after having actually been served with a Notification under either Area 3 or Area 6, the Act considers a dissent to have actually occurred in any event.

There is no deemed dissent arrangement in Section 1 of the Act. A valid dispute can still occur, and surveyors be selected in accordance with Area 10, in regard of works informed under that section however just as concerns actual dissent on specific grounds. An adjacent owner’s reasons for contesting Area 2 and Area 6 works are hardly ever defined prior to the visit of property surveyors and oftentimes not even then.

Where dissent has actually emerged, whether real or deemed, both owners are legally required to appoint an agreed surveyor or, if they can not jointly settle on a bachelor, a property surveyor each and if requested to make such a consultation by the other party, need to do so within 10 days of the demand being served. Failure to comply, immediately gives the owner making the demand the statutory authority to select a surveyor on behalf of the recalcitrant party. This procedure is set out in section 10( 4) of the Act.

Where two property surveyors are appointed, they are required to agree upon the selection, in writing, of a third surveyor who might be called upon by either of the surveyors or either of the parties to figure out the contested matters and make the essential award. The third property surveyor is never ever appointed by anyone but the Act provides the person so chose the very same statutory powers as the two property surveyors.

Third property surveyors are most typically called upon where the two property surveyors have actually reached an impasse in their deliberations over some specific point and typically this can be in respect on the reasonableness of the costs of the property surveyor selected by the adjoining owner. Hardly ever will a 3rd property surveyor be asked to prepare an award in regard of the whole works but may join with one or other of the two surveyors to do so if the requirement occurs.

There is no definition of who can be a property surveyor, but it needs to not be the same person that will monitor the works.

The award will set out the works that can be performed, who will pay the fees for the preparation of the award and evaluation of the works to make sure that they abide by the works, and who will spend for the works. If the work is entirely for the advantage of the structure owner, then they will normally be needed to pay the charges and the cost of the works.

Parties have 2 week to attract the county court if they disagree with the award.

The Act permits access to the adjacent residential or commercial property for the purposes of performing the works whether the adjacent owner gives permission or not, nevertheless they should be provided 2 week notification.

NB: The intro of The Party Wall and so on. Act 1996 (Electronic Communications) Order 2016 implies that from 6 April 2016, notifications and other documents can be served by electronic communications.

The details that Observes must supply in respect of works covered the above areas is different in each case. The requirements of Area 1 and Area 6 Notifications are set out in those sections but the requirements of a Notification relating to Area 2 works is set out in Section 3 of the Act. A valid disagreement can still arise, and property surveyors be selected in accordance with Area 10, in regard of works alerted under that area but just as relates to real dissent on particular grounds. An adjacent owner’s factors for challenging Area 2 and Section 6 works are rarely specified prior to the appointment of property surveyors and in numerous cases not even then.

Where dissent has actually developed, whether actual or considered, both owners are legally obliged to appoint a concurred property surveyor or, if they can not collectively agree on a single individual, a surveyor each and if requested to make such a visit by the other party, need to do so within 10 days of the demand being served.

Related Articles

Around the Web