What is a Party Wall Award?

A Party Wall Award is a contract made between at least two neighbouring occupiers prior to the beginning of construction/building work which is to be undertaken to a party boundary or structure, or where works are being carried out in close distance to a party limit or structure. There are three main types of work which need a Party Wall Property surveyor to perform a Party Wall Award and these are:

  • Line of junction (building a new wall on or along with a border).
  • Party Structure Works (works to an existing party wall such as cutting into, restoring, thickening etc.).
  • Nearby Excavation (excavations to a lower level within either 3m or 6m of an existing building).

In London and across the UK, our skilled business structure surveyors carry out a series of professional surveying services consisting of Party Wall Studies (Party Wall Awards). At Commercial Structure Surveyors we perform Party Wall Studies by knowledgeable and expert Party Wall Surveyors throughout the UK.

Party Wall (WikiPedia)

Typically, the building contractor lays the wall surface along a building line splitting two terraced residences, so that one fifty percent of the wall surface’s thickness exists on each side. This type of wall surface is normally structural. Celebration walls can additionally be formed by two abutting wall surfaces constructed at different times.

Party Wall act

How The Party Wall etc.

Act 1996 Works In simple terms, the Party Wall etc. Act 1996 can be divided into 2 stages; firstly the Notifying Stage and second of all, if required, the Disputed Stage. The first stage is where the Building Owners have a legal responsibility to serve an official Notification detailing the proposed works upon the Adjoining Owners. If the Adjacent Owners are pleased that the Structure Owners’ proposed works will be of no hassle or, posture no risk of damage to their home, the Adjoining Owners just need to confirm, in composing, that they grant the works and the Party Wall and so on. Act 1996 might end there. The 2nd stage would just be set off if the Adjoining Owners had any issues associating with the Building Owners’ proposals or picked to overlook the Notice served by the Structure Owners.
A disagreement would then be considered to have actually arisen and, the structure provided by the Party Wall and so on. Act 1996 allows a resolution so that the Structure Owners might carry out works whilst offering defense to both parties. At the point of a “dispute” having emerged, both the Structure Owners and the Adjoining Owners have to appoint a Party Wall Surveyor to proceed with fixing the conflict. This could be by means of separate surveyor visits or, by consenting to a single property surveyor, called the Agreed Surveyor.
Party Wall Surveyors are responsibility bound to administer the Act impartially as they are, in essence, representatives of the Court. Prior to any conflict developing, Building Owners and Adjacent Owners do not always require the services of a Party Wall Property Surveyor. Nevertheless, The Party Wall Business are frequently commissioned to offer recommendations on the Act and to serve the pertinent Party Wall Notices, guaranteeing they are legally valid. Once selected, the Surveyors will consider the proposed works and agree a Party Wall Award which would detail the structure works and how they should be undertaken. The rights granted within the Party Wall Award go through the Structure Owners making great any damage or, the payment of damages in lieu of making good.

What is a Party Wall Notification?

Building Owners preparing to bring out any of the works specified within the Party Wall etc. Act 1996 have a legal responsibility to serve written Notification on any Adjacent Owner who might be impacted by the Building Owners proposed works.
Mr Herman wanted to fix the Party Fence Wall that divided the two gardens and served a Notice on Mr and Mrs Lehmann. As Mr Herman only served the Notice in his name, Mr and Mrs Lehmann declined to accept the Notice as being valid and argued that as both Mr and Mrs Herman would be related to as Building Owners under the Act, Mrs Herman ought to also be consisted of on the Notice.

What is a Party Wall Award?

A Party Wall Award is a legally binding file in between Building Owners and Adjoining Owners, which has actually been agreed by the selected property surveyor( s), authorising the execution of structure work in accordance with the Act. A Schedule of Condition study of the Adjoining Owners residential or commercial property, although not a particular requirement of the Party Wall and so on. Act 1996, is customary and forms a recommendation document within the Award.

I Already Have Preparation Permission And/ Or Structure Control Approval. Do I Still Required To Follow The Party Wall Act?

The Party Wall and so on. Act 1996 is a totally separate piece of statute legislation to the Town and Country Preparation Act 1990 or the Building Act 1984. For that reason, if your prepared works would be considered notifiable under the Party Wall Act then yes, you would have to follow the treatments set out within the Act. No Local Authority consent or approval would eliminate the legal commitment to serve a Party Wall Notification upon your neighbour( s).

Does The Party Wall Act Cover Garden Fences?

The Act does cover “Party Fence Walls” which are deemed to be a wall of strong structure that sits astride a boundary and not being part of a structure. For that reason, any works to such walls that would be considered notifiable under the Party Wall Act would also apply to Party Fence Walls. Lumber fencing, precast concrete posts with infill panel fencing, etc would not be considered to be a Party Fence Wall, whether astride a boundary or not.

If the Adjacent Owners are pleased that the Building Owners’ proposed works will be of no inconvenience or, posture no hazard of damage to their home, the Adjoining Owners just need to confirm, in writing, that they consent to the works and the Party Wall etc. At the point of a “conflict” having actually developed, both the Building Owners and the Adjacent Owners have to designate a Party Wall Property surveyor to proceed with dealing with the dispute. The Party Wall Company are often commissioned to supply advice on the Act and to serve the appropriate Party Wall Notices, guaranteeing they are lawfully valid. A Party Wall Award is a legally binding document in between Structure Owners and Adjacent Owners, which has been agreed by the appointed surveyor( s), authorising the execution of structure work in accordance with the Act. Any works to such walls that would be deemed notifiable under the Party Wall Act would likewise apply to Party Fence Walls.