What is a Party Wall Award?

A Party Wall Award is an agreement made in between at least 2 neighbouring occupiers prior to the beginning of construction/building work which is to be carried out to a party border or structure, or where works are being undertaken in close distance to a party boundary or structure. There are three primary types of work which need a Party Wall Surveyor to conduct a Party Wall Award and these are:

  • Line of junction (building a new wall on or together with a boundary).
  • Party Structure Functions (works to an existing party wall such as cutting into, rebuilding, thickening etc.).
  • Surrounding Excavation (excavations to a lower level within either 3m or 6m of an existing structure).

In London and throughout the UK, our experienced commercial building surveyors carry out a variety of professional surveying services consisting of Party Wall Studies (Party Wall Awards). At Commercial Building Surveyors we conduct Party Wall Surveys by skilled and expert Party Wall Surveyors throughout the UK.

Party Wall (WikiPedia)

A party wall (occasionally parti-wall or parting wall, also known as common wall or as a demising wall) is a dividing partition between two adjoining buildings that is shared by the occupants of each residence or business. Typically, the builder lays the wall along a property line dividing two terraced houses, so that one half of the wall’s thickness lies on each side. This type of wall is usually structural. Party walls can also be formed by two abutting walls built at different times. The term can be also used to describe a division between separate units within a multi-unit apartment complex. Very often the wall in this case is non-structural but designed to meet established criteria for sound and/or fire protection, i.e. a firewall.

Party Wall

THE PARTY WALL ACT 1996- A BEGINNERS GUIDE

We appreciate that many people wanting to perform works on their home have the requirements of The Party Wall Act thrust upon at a fairly late stage in the pre-construction process. We also comprehend it can be a challenging procedure for those that have actually not experienced it before. Here in Faulkners Surveyors, among our senior property surveyors, offers his “beginners guide” which intends to provide an overview understanding of party walls and the requirements of the Party Wall Act …

What is the Party Wall Act?

The Party Wall etc Act 1996 provides a procedure to follow when building work involves a party wall or party fence wall, some excavations near to neighbouring buildings, and new walls at borders. The Act permits owners to carry out certain particular works, consisting of work to the full thickness of a party wall, whilst at the same time securing the interests of anyone else who might be impacted by that work. The Act is designed to prevent or reduce disputes by making sure homeowner inform their neighbours in advance of certain proposed works.

The Act supplies a system for dealing with disputes and enabling works to proceed. It likewise needs that, where the adjoining owner does not ‘agree’ in writing to the works, a property surveyor or surveyors will figure out the time and way in which those works are carried out.

What is a party wall?

Party walls normally different structures coming from different owners but might include garden walls developed astride a border– known as party fence walls. Where a wall separates 2 different size buildings typically only the part that is used by both homes is a party wall, the rest belongs to the person or individuals on whose land it stands.

The “etc” within The Party Wall etc Act 1996 is so included due to the fact that the arrangements of the Act are not restricted to party walls, they likewise include party structures and party fence walls.

Area 20 of the Act defines each:

” party fence wall” indicates a wall (not being part of a building) which bases on lands of different owners and is utilized or constructed to be used for separating such adjoining lands, but does not consist of a wall built on the land of one owner the artificially formed assistance of which tasks into the land of another owner;

” party structure” implies a party wall and likewise a flooring partition or other structure separating structures or parts of structures approached solely by separate staircases or different entryways;

What is covered by the Act?

There are particular products of work that you can just be done after alerting the adjacent owners and either receiving written agreement of the neighbour or with a Party Wall Award prepared by a surveyor/s.

Notifiable works consist of (however are not limited to):.

If it is proposed to develop a new wall on the line of junction (limit line), notifications are also required. A party wall surveyor will usually be able to verify which work is notifiable and recommendations the notification period and kind of notice needed.

What is not covered by the Act?

The Act relates just to certain specific types of work and is permissive in nature. It must not be seen as a technique of challenging or preventing works and it is not planned to be applied to small tasks that do not affect the structural integrity or loading of a party wall.

It is typically concurred that works such as fixing plug sockets, screwing in shelving or replastering walls are small works and do not need a notification.

Notices.

The workings of the Act are always initiated by the of releasing notices. This is the first stage of the process and, without the issue of valid notifications, no further action can be taken under the provision of the Act.

Written notification should be served on adjoining owners at least 2 months prior to beginning any party wall works (one month for works to the line of junction or excavations). All adjoining owners must be served a notice and there are most likely to be circumstances where there is more than one adjacent residential or commercial property and more than one owner of each residential or commercial property (ie: if the adjacent home is split into flats and owned on a leasehold basis, notifications will be required to both leaseholder and freeholder of all flats impacted by the works). Functions to a party wall, or those impacting a ceiling or flooring, will also require a notice to adjacent owners living above or below.

Valid notices must include the following info as a minimum:.

It is vital to include the correct details on a notice as, if they are deemed invalid, then any subsequent actions are also invalid.

Actions To Notices.

On receipt of a notice, an adjacent owner has three possible strategies:.

If the adjacent does not respond within 14 days then a considered dispute is said to have occurred and the individual carrying out the work needs to appoint a property surveyor to act on the adjacent owners behalf.

If adjacent owners offer written consent to the works as set out within the notices, then there is no disagreement to deal with and no additional requirement for party wall property surveyors or, undoubtedly, the Party Wall Act. Assuming work earnings as detailed within the notice and no damage is triggered, then no further involvement is needed.

Resolving Disputes.

If adjacent owners dissent to the works (or if no action is gotten and a considered dissent has actually emerged) then a dispute has happened which should be solved under the requirements of Section 10 of The Act. It is worth restating that the Act is one of enablement, it is not there to prevent works from taking place and it offers a path to end disagreements at every stage. Where composed agreement is not given, the option the Act offers is for both parties to appoint an ‘agreed surveyor’ who will act impartially or for each owner to appoint a property surveyor who in turn select a 3rd property surveyor. The surveyors then interact to concur the terms under which work might proceed. The property surveyor( s) will review the strategies, notifications and structural information of the works and, after considering the effect of the works, will prepare a contract which sets out the terms under which work can be carried out (the Award).

The Party Wall Award.

The award will generally tape the condition of the appropriate part of adjacent home prior to work starts (this is not a requirement under the Act but is considered good practice and is appropriately provided by a lot of excellent surveyors). The award might also grant access to both homes so that the works can be safely carried out and the surveyor/s can examine work in progress.

Typically, the building owner who began the work spends for all expenses of work and the affordable costs sustained by all celebrations as a result, this will consist of the surveyors fees for both Building Owner and Adjoining Owner.

We value that numerous people wanting to carry out works on their home have the requirements of The Party Wall Act thrust upon at a relatively late stage in the pre-construction procedure. Here, Michael White C.Build.E MCABE MFPWS, one of our senior property surveyors, uses his “novices guide” which aims to provide an overview understanding of party walls and the requirements of the Party Wall Act …

What is the Party Wall Celebration?

The Party Wall etc Act 1996 provides a treatment to follow when building work involves a party wall or party fence wall, some excavations close to neighbouring buildings, and new walls at limits. The Act permits owners to bring out certain particular works, including work to the complete density of a party wall, whilst at the same time protecting the interests of anyone else who might be impacted by that work. Composed notice should be served on adjoining owners at least 2 months before beginning any party wall works (one month for works to the line of junction or excavations).

Related Articles

Around the Web