Faulkners Surveyors As qualified and experienced Party Wall Surveyors we specialise in all Party Wall matters.
We cover every aspect essential to recommend upon and resolve Party Wall issues, such as:

  • Preparing and serving valid Party Wall Notices
  • Acting as the Building Owners Party Wall Property Surveyor
  • Acting as the Adjoining Owners Party Wall Surveyor
  • Acting as the Agreed Party Wall Property Surveyor
  • Undertaking and preparing Schedules of Condition
  • Preparation and negotiation of Party Wall Awards

All our Party Wall Surveyors are experts and operate in accordance with the guidelines set down by the Professors of Party Wall Surveyors.

The Party Wall Act and so on 1996 is law, failure to adhere to this legislation may result in works being illegal.

Party Wall (WikiPedia)

A party wall (occasionally parti-wall or parting wall, also known as common wall or as a demising wall) is a dividing partition between two adjoining buildings that is shared by the occupants of each residence or business. Typically, the builder lays the wall along a property line dividing two terraced houses, so that one half of the wall’s thickness lies on each side. This type of wall is usually structural. Party walls can also be formed by two abutting walls built at different times. The term can be also used to describe a division between separate units within a multi-unit apartment complex. Very often the wall in this case is non-structural but designed to meet established criteria for sound and/or fire protection, i.e. a firewall.

wall party

Party Wall Act

The Party Wall etc. Act 1996 is a making it possible for Act, insofar as it grants the owner of a home the legal right to carry out particular works that might otherwise make up trespass or nuisance.

It likewise seeks to protect the interests of adjacent owners from any potentially negative impacts that such works might have by enforcing a requirement that all adjacent owners be provided prior notice of them.

In addition, the Act attends to a compulsory conflict resolution procedure moderated by a statutorily appointed surveyor or property surveyors if neighbouring owners have issues about the implementation of any proposition so notified.

Particularly, such notification must be served where the owner of a residential or commercial property (called ‘the building owner’) intends to undertake any building and construction work described in Areas 1, 2 and 6 of the Act. Keep in mind that it is just those works that are covered by the Act and the scope is restricted to the following:

The information that Discovers need to provide in regard of works covered the above sections is various in each case. The requirements of Area 1 and Section 6 Notifications are set out in those areas however the requirements of a Notice associating with Section 2 works is set out in Section 3 of the Act. It is necessary to keep in mind that the credibility of any notification not offering all the pertinent information or served in the incorrect manner, could be open up to challenge in Court.

There is no standard type of Notification although many individuals use those released by the RICS or versions added to the explanatory booklet released by the Department for Communities and City Government. Supplied all the information needed by the relevant section of the Act is present, a simple letter would be similarly valid.

Depending on the situations of any offered task there might be more than one adjacent owner on whom discover needs to be served in regard of the exact same work and, when it comes to deep excavations, an Adjoining Owner may be besides an instant neighbour. It is always preferable to talk about the designated works with adjacent owners prior to serving them with official composed notice – a proposal well explained might ease issues enough to prevent a conflict emerging and avoid the requirement to designate surveyors.

There are two exceptions where the need to serve notice may be prevented:

  1. De minimis works: The federal government’s explanatory brochure says that some deal with a party wall may be so small that service of notice under the Act would be usually regarded as not necessary and give as examples works not likely to affect the structural strength or assistance functions of a party structure or trigger damage to the neighbours side of it, such as re-plastering, shallow chasing for electrical circuitry or placing power sockets, and screws to support shelves, cooking area cupboards, and the like.
  2. Works under Section 2 of the Act provided that written consent is acquired from all Adjacent Owners and Occupiers prior to work commences.

The 3 kinds of Notice are known, respectively as:

A party structure notice must be served at least 2 months before the date on which it is proposed to begin that work. The other two notices need to be served at least one month prior to work beginning.

The mandatory information which Sees should include are as follows:

Most of the pro-forma notices in use include the following details as a matter of course regardless of the kind of notification:

Area 10 of the Act specifies that where an adjacent owner does not approval in writing to works informed by the structure owner under Areas 3 and 6, both celebrations need to either settle on the consultation of a single surveyor to act for both of them (referred to as the Agreed Property Surveyor), or each designate their own surveyor, to figure out by award matters in dispute in between the parties.

Where a job is straightforward, this may only include factor to consider of the time and way in which those works are to be performed. In more complex schemes, thought will need to be offered to a commensurately greater number of aspects and indeed appointed surveyors have the statutory jurisdiction to make an award in respect of any matter connected with any work to which the act relates.

The exact same treatment is used to deal with any subsequent conflicts between neighbouring owners that may occur in relation to the informed works, consisting of any loss or damage suffered by an adjoining owner as a result of their execution.

Inaction on the part of the adjoining owner does not halt the statutory process. A disagreement can emerge by an adjacent owner actively dissenting, that is, interacting to the building owner an objection in regard of some matter developing out of or incidental to the works – the means of making that objection are trivial, however if he stays silent, neither consenting nor dissenting for a period of 14 days after having actually been served with a Notification under either Section 3 or Area 6, the Act deems a dissent to have actually emerged in any event.

There is no considered dissent arrangement in Section 1 of the Act. A valid conflict can still arise, and property surveyors be appointed in accordance with Area 10, in respect of works alerted under that section however only as relates to real dissent on specific premises. An adjoining owner’s factors for disputing Area 2 and Section 6 works are rarely defined prior to the visit of property surveyors and in most cases not even then.

Where dissent has actually arisen, whether real or deemed, both owners are lawfully obliged to appoint a concurred property surveyor or, if they can not jointly settle on a bachelor, a property surveyor each and if requested to make such an appointment by the other party, must do so within 10 days of the request being served. Failure to comply, immediately gives the owner making the demand the statutory authority to designate a property surveyor on behalf of the recalcitrant party. This procedure is set out in area 10( 4) of the Act.

Where two property surveyors are designated, they are required to agree upon the choice, in composing, of a third surveyor who may be hired by either of the property surveyors or either of the celebrations to identify the contested matters and make the needed award. The 3rd property surveyor is never ever appointed by anyone but the Act provides the individual so chose the very same statutory powers as the two property surveyors.

3rd property surveyors are most commonly called upon where the two surveyors have actually reached an impasse in their considerations over some specific point and typically this can be in regard on the reasonableness of the fees of the surveyor designated by the adjoining owner. Rarely will a third property surveyor be asked to draw up an award in respect of the whole works but might join with one or other of the two surveyors to do so if the need occurs.

There is no meaning of who can be a property surveyor, but it ought to not be the same individual that will supervise the works.

The award will set out the works that can be carried out, who will pay the charges for the preparation of the award and examination of the works to guarantee that they adhere to the works, and who will pay for the works. They will typically be required to pay the charges and the expense of the works if the work is solely for the advantage of the building owner.

If they disagree with the award, parties have 14 days to appeal to the county court.

The Act enables access to the adjoining residential or commercial property for the functions of performing the works whether the adjacent owner allows or not, however they need to be provided 14 days notice.

NB: The intro of The Party Wall and so on. Act 1996 (Electronic Communications) Order 2016 indicates that from 6 April 2016, notices and other documents can be served by electronic communications.

The info that Sees need to offer in regard of works covered the above sections is various in each case. The requirements of Area 1 and Section 6 Notices are set out in those sections however the requirements of a Notification relating to Section 2 works is set out in Area 3 of the Act. A valid conflict can still arise, and surveyors be selected in accordance with Section 10, in respect of works alerted under that section but just as concerns real dissent on particular premises. An adjoining owner’s factors for contesting Area 2 and Area 6 works are hardly ever defined prior to the consultation of surveyors and in many cases not even then.

Where dissent has emerged, whether actual or deemed, both owners are legally obliged to select an agreed surveyor or, if they can not collectively agree on a single person, a property surveyor each and if asked for to make such a consultation by the other party, need to do so within 10 days of the request being served.