PARTY WALL SURVEYORS

Faulkners Surveyors is an independent firm of building property surveyors that specialise in the

Party Wall and so on. Act 1996 acting for Building Owners, Adjacent Owners and as the Agreed Property Surveyor throughout London and the Home Counties.

Party Wall (WikiPedia)

A party wall (occasionally parti-wall or parting wall, also known as common wall or as a demising wall) is a dividing partition between two adjoining buildings that is shared by the occupants of each residence or business. Typically, the builder lays the wall along a property line dividing two terraced houses, so that one half of the wall’s thickness lies on each side. This type of wall is usually structural. Party walls can also be formed by two abutting walls built at different times. The term can be also used to describe a division between separate units within a multi-unit apartment complex. Very often the wall in this case is non-structural but designed to meet established criteria for sound and/or fire protection, i.e. a firewall.

wall party

Party Wall Act

The Party Wall etc. Act 1996 is a making it possible for Act, insofar as it gives the owner of a property the legal right to carry out particular works that may otherwise make up trespass or annoyance.

Nevertheless, it likewise looks for to secure the interests of adjoining owners from any possibly adverse effects that such works may have by enforcing a requirement that all adjoining owners be provided prior notification of them.

In addition, the Act provides for a mandatory disagreement resolution procedure mediated by a statutorily appointed surveyor or property surveyors if neighbouring owners have issues about the application of any proposal so notified.

Specifically, such notice should be served where the owner of a home (known as ‘the building owner’) means to carry out any building and construction work explained in Sections 1, 2 and 6 of the Act. Keep in mind that it is only those works that are covered by the Act and the scope is restricted to the following:

The details that Notices need to provide in respect of works covered the above sections is various in each case. The requirements of Section 1 and Section 6 Notifications are set out in those sections however the requirements of a Notification connecting to Area 2 works is set out in Section 3 of the Act. It is essential to keep in mind that the credibility of any notification not providing all the pertinent information or served in the inaccurate manner, could be open up to challenge in Court.

There is no standard form of Notification although many people use those published by the RICS or variations added to the explanatory booklet released by the Department for Communities and Local Government. However, provided all the info needed by the relevant section of the Act is present, a simple letter would be similarly valid.

Depending on the situations of any provided job there might be more than one adjacent owner on whom notice requirements to be served in regard of the exact same work and, when it comes to deep excavations, an Adjacent Owner might be aside from an immediate neighbour. It is always preferable to discuss the intended works with adjoining owners prior to serving them with formal written notice – a proposition well described may minimize concerns adequate to prevent a disagreement emerging and avoid the requirement to appoint surveyors.

There are two exceptions where the need to serve notice might be prevented:

  1. De minimis works: The federal government’s explanatory brochure states that some deal with a party wall might be so small that service of notice under the Act would be generally regarded as not necessary and give as examples works unlikely to affect the structural strength or assistance functions of a party structure or trigger damage to the neighbours side of it, such as re-plastering, shallow chasing for electrical circuitry or inserting power sockets, and screws to support racks, kitchen area cupboards, and so forth.
  2. Works under Section 2 of the Act supplied that composed permission is obtained from all Adjacent Owners and Occupiers prior to work commences.

The 3 kinds of Notice are known, respectively as:

A party structure notice must be served a minimum of two months prior to the date on which it is proposed to begin that work. The other 2 notices should be served at least one month prior to work starting.

The mandatory information which Sees must include are as follows:

The majority of the pro-forma notices in use include the following details as a matter of course no matter the kind of notice:

Area 10 of the Act specifies that where an adjoining owner does not authorization in writing to works alerted by the building owner under Sections 3 and 6, both parties need to either agree on the visit of a single surveyor to act for both of them (called the Agreed Surveyor), or each appoint their own surveyor, to determine by award matters in dispute between the celebrations.

Where a project is straightforward, this might just include factor to consider of the time and way in which those works are to be carried out. In more complex plans, believed will need to be given to a commensurately greater number of elements and undoubtedly appointed property surveyors have the statutory jurisdiction to make an award in regard of any matter connected with any work to which the act relates.

The same procedure is used to deal with any subsequent disagreements between neighbouring owners that might develop in relation to the informed works, consisting of any loss or damage suffered by an adjoining owner as a result of their execution.

Inaction on the part of the adjacent owner does not halt the statutory procedure. A dispute can emerge by an adjoining owner actively dissenting, that is, communicating to the building owner an objection in respect of some matter arising out of or incidental to the works – the means of making that objection are trivial, but if he stays quiet, neither consenting nor dissenting for a period of 14 days after having actually been served with a Notice under either Section 3 or Section 6, the Act deems a dissent to have actually developed in any event.

There is no deemed dissent provision in Section 1 of the Act. A legitimate conflict can still arise, and surveyors be designated in accordance with Area 10, in regard of works informed under that area however just as regards actual dissent on specific grounds. An adjacent owner’s reasons for contesting Section 2 and Section 6 works are seldom specified prior to the appointment of surveyors and in many cases not even then.

Where dissent has actually occurred, whether real or deemed, both owners are legally obliged to appoint a concurred surveyor or, if they can not collectively settle on a single person, a surveyor each and if requested to make such a visit by the other party, need to do so within 10 days of the demand being served. Failure to comply, immediately offers the owner making the request the statutory authority to designate a property surveyor on behalf of the recalcitrant party. This treatment is set out in area 10( 4) of the Act.

Where two surveyors are selected, they are required to agree upon the selection, in composing, of a third surveyor who may be hired by either of the surveyors or either of the parties to figure out the disputed matters and make the needed award. The third property surveyor is never appointed by anyone however the Act gives the person so picked the very same statutory powers as the two surveyors.

3rd surveyors are most typically called upon where the two property surveyors have actually reached a deadlock in their deliberations over some specific point and often this can be in regard on the reasonableness of the costs of the property surveyor selected by the adjoining owner. Seldom will a 3rd surveyor be asked to prepare an award in respect of the whole works but might join with one or other of the two surveyors to do so if the requirement develops.

There is no meaning of who can be a property surveyor, but it must not be the same person that will monitor the works.

The award will set out the works that can be carried out, who will pay the charges for the preparation of the award and inspection of the works to ensure that they comply with the works, and who will spend for the works. They will normally be required to pay the charges and the cost of the works if the work is exclusively for the benefit of the building owner.

Celebrations have 14 days to interest the county court if they disagree with the award.

The Act allows access to the adjoining property for the purposes of carrying out the works whether the adjoining owner gives permission or not, however they must be provided 14 days notification.

NB: The intro of The Party Wall etc. Act 1996 (Electronic Communications) Order 2016 indicates that from 6 April 2016, notices and other files can be served by electronic communications.

The information that Sees must provide in regard of works covered the above sections is different in each case. The requirements of Section 1 and Section 6 Notices are set out in those sections however the requirements of a Notice relating to Section 2 works is set out in Section 3 of the Act. A valid conflict can still occur, and property surveyors be appointed in accordance with Area 10, in regard of works informed under that area but only as concerns actual dissent on particular premises. An adjacent owner’s factors for disputing Section 2 and Section 6 works are rarely defined prior to the visit of surveyors and in numerous cases not even then.

Where dissent has emerged, whether actual or considered, both owners are lawfully required to select an agreed surveyor or, if they can not jointly concur on a single person, a surveyor each and if asked for to make such a visit by the other party, must do so within 10 days of the demand being served.

Related Articles

Around the Web