What is a Party Wall Award?

The process and requirements of a Party Wall Award are as set out in the Party Wall and so on. Act 1996. A Party Wall Award is a contract made in between at least two neighbouring occupiers prior to the beginning of construction/building work which is to be undertaken to a party boundary or structure, or where works are being carried out in close proximity to a party limit or structure. There are three primary types of work which need a Party Wall Property surveyor to carry out a Party Wall Award and these are:

  • Line of junction (developing a new wall on or along with a border).
  • Party Structure Works (works to an existing party wall such as cutting into, rebuilding, thickening and so on).
  • Adjacent Excavation (excavations to a lower level within either 3m or 6m of an existing structure).

In London and throughout the UK, our skilled industrial building property surveyors carry out a variety of professional surveying services including Party Wall Studies (Party Wall Awards). At Commercial Structure Surveyors we perform Party Wall Surveys by expert and knowledgeable Party Wall Surveyors throughout the UK.

Party Wall (WikiPedia)

Commonly, the contractor lays the wall surface along a building line separating two terraced residences, so that one half of the wall’s density lies on each side. This kind of wall is typically structural. Event wall surfaces can also be formed by two abutting walls built at various times.

wall party

Party Wall Act

The Party Wall etc. Act 1996 is an enabling Act, insofar as it approves the owner of a property the legal right to undertake certain works that may otherwise constitute trespass or problem.

Nevertheless, it likewise looks for to safeguard the interests of adjoining owners from any possibly adverse impacts that such works might have by enforcing a requirement that all adjacent owners be provided prior notification of them.

In addition, the Act offers a necessary conflict resolution treatment moderated by a statutorily selected property surveyor or property surveyors if neighbouring owners have concerns about the application of any proposition so notified.

Particularly, such notice needs to be served where the owner of a residential or commercial property (called ‘the structure owner’) plans to undertake any construction work explained in Areas 1, 2 and 6 of the Act. Keep in mind that it is just those works that are covered by the Act and the scope is restricted to the following:

The information that Sees need to offer in regard of works covered the above sections is different in each case. The requirements of Area 1 and Area 6 Notices are set out in those areas however the requirements of a Notice relating to Area 2 works is set out in Section 3 of the Act. It is very important to keep in mind that the validity of any notice not supplying all the relevant info or served in the incorrect way, could be open up to challenge in Court.

There is no standard kind of Notice although lots of people utilize those published by the RICS or versions appended to the explanatory brochure issued by the Department for Communities and Local Government. Offered all the details needed by the relevant section of the Act is present, an easy letter would be equally legitimate.

Depending on the scenarios of any given job there might be more than one adjacent owner on whom observe needs to be served in respect of the exact same work and, when it comes to deep excavations, an Adjoining Owner may be aside from an immediate neighbour. It is constantly preferable to talk about the desired works with adjoining owners before serving them with official composed notification – a proposal well discussed might relieve issues sufficient to prevent a dispute developing and avoid the need to designate property surveyors.

There are two exceptions where the requirement to serve notice might be avoided:

  1. De minimis works: The federal government’s explanatory brochure states that some works on a party wall might be so minor that service of notification under the Act would be generally considered not essential and give as examples works unlikely to impact the structural strength or assistance functions of a party structure or trigger damage to the neighbours side of it, such as re-plastering, shallow chasing for electrical wiring or placing power sockets, and screws to support shelves, kitchen area cabinets, and so forth.
  2. Works under Section 2 of the Act supplied that composed permission is gotten from all Adjacent Owners and Occupiers before work commences.

The 3 types of Notification are understood, respectively as:

A party structure notification need to be served at least 2 months before the date on which it is proposed to begin that work. The other 2 notices should be served a minimum of one month prior to work beginning.

The necessary info which Observes should consist of are as follows:

Most of the pro-forma notices in use include the following info as a matter of course no matter the kind of notification:

Area 10 of the Act states that where an adjacent owner does not approval in writing to works informed by the structure owner under Areas 3 and 6, both celebrations must either settle on the consultation of a single property surveyor to act for both of them (known as the Agreed Property Surveyor), or each select their own surveyor, to identify by award matters in dispute between the celebrations.

Where a task is straightforward, this might only include consideration of the time and way in which those works are to be performed. In more complex plans, believed will have to be provided to a commensurately greater number of elements and certainly selected property surveyors have the statutory jurisdiction to make an award in respect of any matter gotten in touch with any work to which the act relates.

The same procedure is used to deal with any subsequent conflicts in between neighbouring owners that may emerge in relation to the notified works, consisting of any loss or damage suffered by an adjacent owner as a result of their execution.

Inactiveness on the part of the adjacent owner does not halt the statutory process. A disagreement can emerge by an adjoining owner actively dissenting, that is, communicating to the building owner an objection in respect of some matter occurring out of or incidental to the works – the means of making that objection are trivial, however if he stays quiet, neither dissenting nor consenting for a duration of 14 days after having actually been served with a Notification under either Section 3 or Section 6, the Act considers a dissent to have emerged in any event.

There is no deemed dissent arrangement in Section 1 of the Act. A legitimate disagreement can still occur, and surveyors be selected in accordance with Area 10, in respect of works informed under that section but only as regards real dissent on particular premises. An adjacent owner’s reasons for disputing Section 2 and Section 6 works are hardly ever specified prior to the visit of property surveyors and oftentimes not even then.

Where dissent has developed, whether real or deemed, both owners are legally obliged to select an agreed property surveyor or, if they can not collectively settle on a single person, a property surveyor each and if requested to make such a consultation by the other party, need to do so within 10 days of the request being served. Failure to comply, instantly provides the owner making the demand the statutory authority to select a property surveyor on behalf of the recalcitrant party. This procedure is set out in area 10( 4) of the Act.

Where two surveyors are appointed, they are required to agree upon the selection, in composing, of a 3rd surveyor who may be called upon by either of the property surveyors or either of the parties to determine the challenged matters and make the required award. The 3rd surveyor is never ever appointed by anybody however the Act gives the person so selected the very same statutory powers as the two property surveyors.

Third property surveyors are most commonly called upon where the two property surveyors have actually reached an impasse in their deliberations over some particular point and typically this can be in respect on the reasonableness of the costs of the surveyor appointed by the adjoining owner. Rarely will a third surveyor be asked to draw up an award in regard of the entire works however might accompany one or other of the two surveyors to do so if the requirement emerges.

There is no meaning of who can be a surveyor, but it should not be the same person that will supervise the works.

The award will set out the works that can be carried out, who will pay the costs for the preparation of the award and examination of the works to guarantee that they adhere to the works, and who will spend for the works. They will generally be required to pay the charges and the cost of the works if the work is exclusively for the benefit of the building owner.

Parties have 14 days to interest the county court if they disagree with the award.

The Act enables access to the adjacent residential or commercial property for the functions of carrying out the works whether the adjacent owner permits or not, nevertheless they need to be provided 2 week notification.

NB: The introduction of The Party Wall etc. Act 1996 (Electronic Communications) Order 2016 indicates that from 6 April 2016, notices and other documents can be served by electronic interactions.

The info that Discovers must provide in respect of works covered the above sections is various in each case. The requirements of Section 1 and Area 6 Notices are set out in those areas however the requirements of a Notification relating to Section 2 works is set out in Area 3 of the Act. A valid conflict can still arise, and property surveyors be designated in accordance with Section 10, in regard of works notified under that section but just as concerns real dissent on specific grounds. An adjoining owner’s reasons for disputing Area 2 and Section 6 works are hardly ever defined prior to the consultation of surveyors and in many cases not even then.

Where dissent has occurred, whether actual or considered, both owners are lawfully required to designate an agreed surveyor or, if they can not jointly agree on a single person, a surveyor each and if requested to make such a visit by the other party, should do so within 10 days of the demand being served.