At Faulkners Surveyors we perform Party Wall Surveys by expert and knowledgeable Party Wall Surveyors throughout the UK.

What is a Party Wall Award?

A Party Wall Award is an arrangement made in between at least two neighbouring occupiers prior to the beginning of construction/building work which is to be carried out to a party limit or structure, or where works are being undertaken in close distance to a party border or structure. There are three main types of work which need a Party Wall Surveyor to conduct a Party Wall Award and these are:

  • Line of junction (constructing a brand-new wall on or together with a boundary).
  • Party Structure Works (works to an existing party wall such as cutting into, restoring, thickening etc.).
  • Nearby Excavation (excavations to a lower level within either 3m or 6m of an existing building).

In London and across the UK, our knowledgeable business structure property surveyors perform a range of expert surveying services consisting of Party Wall Surveys (Party Wall Awards). At Commercial Structure Surveyors we carry out Party Wall Surveys by experienced and professional Party Wall Surveyors throughout the UK.

Party Wall (WikiPedia)

A party wall (occasionally parti-wall or parting wall, also referred to as usual wall surface or as a demising wall) is a separating dividers in between two adjacent buildings that is shared by the residents of each residence or company. Typically, the building contractor lays the wall surface along a residential or commercial property line splitting 2 terraced homes, to make sure that one fifty percent of the wall surface’s thickness pushes each side. This sort of wall is normally architectural. Celebration wall surfaces can also be created by 2 abutting walls constructed at different times. The term can be additionally utilized to describe a division in between separate units within a multi-unit apartment building. Very frequently the wall in this instance is non-structural however developed to satisfy well-known criteria for noise and/or fire security, i.e. a firewall program.

wall party

Party Wall Act

The Party Wall etc. Act 1996 is an enabling Act, insofar as it approves the owner of a property the legal right to undertake certain works that may otherwise constitute trespass or nuisance.

However, it also looks for to secure the interests of adjacent owners from any possibly negative results that such works may have by enforcing a requirement that all adjoining owners be given prior notice of them.

In addition, the Act offers a mandatory conflict resolution procedure mediated by a statutorily selected surveyor or property surveyors if neighbouring owners have issues about the execution of any proposition so notified.

Specifically, such notification must be served where the owner of a property (called ‘the structure owner’) plans to undertake any building work described in Sections 1, 2 and 6 of the Act. Note that it is only those works that are covered by the Act and the scope is restricted to the following:

The details that Observes need to provide in regard of works covered the above areas is different in each case. The requirements of Section 1 and Section 6 Notices are set out in those areas however the requirements of a Notification connecting to Section 2 works is set out in Area 3 of the Act. It is very important to note that the validity of any notice not supplying all the appropriate information or served in the inaccurate way, could be open to challenge in Court.

There is no basic kind of Notification although many individuals use those published by the RICS or versions added to the explanatory pamphlet provided by the Department for Communities and Local Government. Offered all the info needed by the appropriate area of the Act is present, a simple letter would be equally legitimate.

Depending on the circumstances of any provided task there may be more than one adjoining owner on whom discover needs to be served in regard of the exact same work and, when it comes to deep excavations, an Adjoining Owner might be besides an immediate neighbour. It is constantly more suitable to discuss the designated deal with adjacent owners before serving them with formal written notification – a proposal well explained may ease concerns enough to prevent a conflict occurring and avoid the need to select surveyors.

There are 2 exceptions where the requirement to serve notice might be avoided:

  1. De minimis works: The government’s explanatory booklet states that some deal with a party wall may be so small that service of notice under the Act would be generally considered not essential and give as examples works unlikely to impact the structural strength or assistance functions of a party structure or cause damage to the neighbours side of it, such as re-plastering, shallow chasing for electrical wiring or inserting power sockets, and screws to support racks, kitchen cupboards, and the like.
  2. Functions under Area 2 of the Act offered that written consent is acquired from all Adjoining Owners and Occupiers prior to work commences.

The three kinds of Notice are known, respectively as:

A party structure notice should be served at least 2 months prior to the date on which it is proposed to begin that work. The other two notices need to be served at least one month prior to work starting.

The mandatory details which Notices need to consist of are as follows:

The majority of the pro-forma notifications in use consist of the following information as a matter of course regardless of the type of notice:

Area 10 of the Act states that where an adjacent owner does not authorization in writing to works alerted by the building owner under Sections 3 and 6, both parties must either agree on the consultation of a single surveyor to act for both of them (referred to as the Agreed Surveyor), or each designate their own property surveyor, to figure out by award matters in dispute in between the parties.

Where a job is straightforward, this might only involve consideration of the time and manner in which those works are to be carried out. In more complex plans, believed will have to be given to a commensurately greater number of factors and indeed selected property surveyors have the statutory jurisdiction to make an award in respect of any matter connected with any work to which the act relates.

The exact same treatment is used to fix any subsequent conflicts between neighbouring owners that might arise in relation to the informed works, including any loss or damage suffered by an adjoining owner as a result of their execution.

Inaction on the part of the adjoining owner does not halt the statutory procedure. A conflict can emerge by an adjacent owner actively dissenting, that is, communicating to the structure owner an objection in respect of some matter emerging out of or incidental to the works – the ways of making that objection are not important, but if he stays silent, neither dissenting nor consenting for a duration of 2 week after having actually been served with a Notice under either Area 3 or Section 6, the Act considers a dissent to have actually emerged in any event.

There is no deemed dissent arrangement in Section 1 of the Act. A legitimate dispute can still emerge, and property surveyors be designated in accordance with Area 10, in respect of works informed under that section but just as relates to real dissent on specific premises. An adjoining owner’s reasons for challenging Section 2 and Section 6 works are hardly ever defined prior to the consultation of surveyors and oftentimes not even then.

Where dissent has actually emerged, whether real or considered, both owners are legally obliged to select an agreed property surveyor or, if they can not jointly agree on a bachelor, a surveyor each and if asked for to make such a consultation by the other party, should do so within 10 days of the request being served. Failure to comply, instantly provides the owner making the request the statutory authority to designate a property surveyor on behalf of the recalcitrant party. This treatment is set out in section 10( 4) of the Act.

Where two surveyors are designated, they are obliged to agree upon the selection, in writing, of a 3rd property surveyor who may be hired by either of the surveyors or either of the celebrations to identify the contested matters and make the essential award. The 3rd surveyor is never appointed by anybody but the Act provides the person so picked the same statutory powers as the two surveyors.

3rd surveyors are most typically called upon where the two property surveyors have actually reached an impasse in their deliberations over some specific point and often this can be in respect on the reasonableness of the fees of the surveyor appointed by the adjoining owner. Rarely will a 3rd surveyor be asked to draw up an award in regard of the entire works however might accompany one or other of the two property surveyors to do so if the need develops.

There is no meaning of who can be a property surveyor, but it needs to not be the same person that will supervise the works.

The award will set out the works that can be carried out, who will pay the costs for the preparation of the award and evaluation of the works to ensure that they adhere to the works, and who will spend for the works. They will generally be required to pay the charges and the cost of the works if the work is solely for the benefit of the building owner.

If they disagree with the award, celebrations have 14 days to appeal to the county court.

The Act permits access to the adjoining home for the functions of performing the works whether the adjoining owner gives permission or not, however they should be offered 14 days notice.

NB: The introduction of The Party Wall and so on. Act 1996 (Electronic Communications) Order 2016 suggests that from 6 April 2016, notices and other files can be served by electronic communications.

The info that Discovers need to offer in respect of works covered the above sections is different in each case. The requirements of Area 1 and Section 6 Notifications are set out in those areas however the requirements of a Notice relating to Section 2 works is set out in Section 3 of the Act. A legitimate conflict can still emerge, and property surveyors be designated in accordance with Section 10, in regard of works alerted under that section but only as regards real dissent on specific premises. An adjacent owner’s factors for contesting Section 2 and Section 6 works are seldom specified prior to the visit of property surveyors and in many cases not even then.

Where dissent has developed, whether real or considered, both owners are legally obliged to select an agreed surveyor or, if they can not collectively agree on a single person, a property surveyor each and if requested to make such an appointment by the other party, should do so within 10 days of the request being served.